! Alert

Governors Island will be open until 7 PM on Monday, October 14 with Manhattan and Brooklyn ferries will running on a weekend schedule.

Governors Island will be open until 7 PM on Monday, October 14 with Manhattan and Brooklyn ferries will running on a weekend schedule.

Request for Proposals for Governors Island BMB Gantries & Slip 7 Ceiling Painting

Issue Date:
September 26, 2019
Last Updated:
September 26, 2019

The Trust for Governors Island and the LiRo Program and Construction Management invites contractors to submit proposals to perform surface preparation and coating of gantry towers at the Governors Island ferry terminal (Battery Maritime Building) designed for long-term protection of the gantries and ceiling.

RFP issued: September 26, 2019
Pre-Proposal meeting: October 7, 2019
Questions due: October 14, 2019
Final proposals due: November 4, 2019 at 3:00 PM

Request for Proposals for Governors Island Secondary Electric Rehabilitation

Issue Date:
September 26, 2019
Last Updated:
September 26, 2019

The Trust for Governors Island and the LiRo Program and Construction Management invites electrical contractors to submit proposals to perform rehabilitation and upgrade services on the Island’s secondary electrical system.

RFP issued: September 23, 2019
Pre-Proposal meeting: October 8, 2019 at 10:15 AM
Questions due: October 21, 2019 at 5:00 PM
Final proposals due: November 15, 2019 at 3:00 PM